RIDF Dashboard
Government of India created the Rural Infrastructure Development Fund (RIDF) in NABARD in 1995-96. Under this scheme NABARD releases loan to State Governments for selected projects at low interest rate, which will be repaid to NABARD as per agreement with the State Governments. RIDF scheme was started with an initial corpus of Rs.2,000 crore.With the allocation of Rs.40,000 crore for 2021-22 under RIDF XXVII, the cumulative allocation has reached Rs.4,18,408.73 crore, including Rs. 18,500 crore under Bharat Nirman. Under RIDF, Department of Fisheries, Government of Karnataka takes up projects for Construction, Maintenance and Renovation of fisheries harbours, jetties and landing centers, maintenance of fisheries link roads, Construction of Fish Markets, Renovation and upgradation of fish seed farms. Details and current status of Fisheries projects from 2013-14 (Tranche 18) to 2018-19 (Tranche-24) are provided in this report. The department has proposed to take up further RIDF Projects in Tranche 28 (2022-23) which is under consideration.
75
₹116.15 in Crores
₹
in Crores₹98.14 in Crores
₹10.06 in Crores
ID | Work | Years | Tranche | District | Taluk | Estimate cost | Nabard Assistance | Amt rel inprevious session | Amt rel in current session | Amt rel | Expenditure | Rec released | Balance claim | Status | Remark |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Cont of Fisheries Jetty at Ullala Kotepura | 2012-13 | RIDF-18 | Dakshina Kannada | Mangalore | 1.25 | 1.19 | 1.32 | 1.32 | 1.32 | 1.32 | 1.18 | 0.00 | Completed | PCR submitted |
2 | Extension of Fish Landing Jetty towards west side at Belekeri | 2012-13 | RIDF-18 | UTTAR KANNADA | Ankola | 2.15 | 2.04 | 2.46 | 2.46 | 2.46 | 2.46 | 2.04 | 0.00 | Completed | PCR submitted |
3 | Const of Fishinf Jetty near Alvedande | 2012-13 | RIDF-18 | UTTAR KANNADA | Kumta | 0.85 | 0.81 | 0.71 | 0.71 | 0.71 | 0.71 | 0.68 | 0.00 | Completed | PCR submitted |
4 | Const of Fishing Jetty at Kagal Hini | 2012-13 | RIDF-18 | UTTAR KANNADA | Kumta | 0.75 | 0.71 | 0.74 | 0.74 | 0.74 | 0.74 | 0.70 | 0.00 | Completed | PCR submitted |
5 | Constn. of minor fishing jetty @ Hegadeambigarkeri | 2013-14 | RIDF-19 | UTTAR KANNADA | Kumta | 0.85 | 0.81 | 0.89 | 0.89 | 0.89 | 0.89 | 0.80 | 0.00 | Completed | PCR submitted |
6 | Constn. of fish landing jetty @ Harwada | 2013-14 | RIDF-19 | UTTAR KANNADA | Ankola | 3.00 | 2.85 | 3.01 | 3.01 | 3.01 | 3.01 | 2.85 | 0.00 | Completed | PCR submitted |
7 | Constn. of minor fishing jetty @ Kimani | 2013-14 | RIDF-19 | UTTAR KANNADA | Kumta | 1.15 | 1.09 | 1.24 | 1.24 | 1.24 | 1.24 | 1.09 | 0.00 | Completed | PCR submitted |
8 | Constn. of Idle berthing jetty @ Boloor bokkapatna near Sultan Batteryfish landing jetty @ Harwada | 2013-14 | RIDF-19 | DAKSHINA KANNADA | Mangalore | 5.00 | 4.75 | 3.40 | 3.40 | 3.40 | 3.40 | 3.23 | 0.00 | Completed | PCR submitted |
9 | Extn. Of fisheries jetty @ Kotepura in Ullala | 2013-14 | RIDF-19 | DAKSHINA KANNADA | Mangalore | 3.50 | 3.33 | 3.09 | 3.09 | 3.09 | 3.09 | 2.94 | 0.00 | Completed | PCR submitted |
10 | Extension of Murudeshwara Bengre Beach road | 2014-15 | RIDF-20 | UTTAR KANNADA | Bhatkal | 3.00 | 2.40 | 2.87 | 2.87 | 2.87 | 2.87 | 2.30 | 0.00 | Completed | PCR submitted |
11 | Construction of Bridge at Kerihalli near Uppunda village | 2014-15 | RIDF-20 | UDUPI | Kundapur | 0.85 | 0.68 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | dropped | dropped |
12 | Construction of Bridge at Ammanavarathoppalui near Uppunda village | 2014-15 | RIDF-20 | UDUPI | Kundapur | 0.50 | 0.40 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | dropped | dropped |
13 | Extension of Jety (Quay) at Bhatkal Fishery Harbour in Bhatkal | 2014-15 | RIDF-20 | UTTAR KANNADA | Bhatkal | 4.98 | 4.73 | 4.96 | 4.96 | 4.96 | 4.96 | 4.71 | 0.00 | Completed | PCR submitted |
14 | Extension of Jety at karwar-baitkol Harbour in Karwar | 2014-15 | RIDF-20 | UTTAR KANNADA | Karwar | 4.98 | 4.73 | 2.21 | 2.21 | 2.21 | 2.21 | 2.10 | 0.00 | Completed | PCR submitted |
15 | Construction of Fish Jetty at Munda Sasihithlu near Mulki | 2014-15 | RIDF-20 | DAKSHINA KANNADA | Mangalore | 4.50 | 4.28 | 4.50 | 4.50 | 4.50 | 4.50 | 4.28 | 0.00 | Completed | PCR submitted |
16 | Improvements to selected reaches of Thenka Fisheries road in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.15 | 0.12 | 0.15 | 0.15 | 0.15 | 0.15 | 0.12 | 0.00 | Completed | PCR submitted |
17 | Impts. to road from new Marigude (NH) to Garadi in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.15 | 0.12 | 0.14 | 0.14 | 0.14 | 0.14 | 0.11 | 0.00 | Completed | PCR submitted |
18 | Impts. to road from NH near Laxmijanardhana temple to sea parallel road, Narayana guru road Junction in Kaup constitutency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.20 | 0.16 | 0.15 | 0.15 | 0.15 | 0.15 | 0.12 | 0.00 | Completed | PCR submitted |
19 | Impts. to road from Kadipatna Rehaman's House to Nadipatna Bhajana Mundhir in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.10 | 0.08 | 0.07 | 0.07 | 0.07 | 0.07 | 0.06 | 0.00 | Completed | PCR submitted |
20 | Impts. to road from Pangala church Kaipunjal at Uliyaroli in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.25 | 0.20 | 0.25 | 0.25 | 0.25 | 0.25 | 0.20 | 0.00 | Completed | PCR submitted |
21 | Impts. to Fisheries road from Hejmade Kodi School to Nadikuduru Jarandaya Temple at Hemjadi in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.20 | 0.16 | 0.20 | 0.20 | 0.20 | 0.20 | 0.16 | 0.00 | Completed | PCR submitted |
22 | Impts.to Kote Kamanu Fisheries road at Kote in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.10 | 0.08 | 0.07 | 0.07 | 0.07 | 0.07 | 0.06 | 0.00 | Completed | PCR submitted |
23 | Impts to Fishries road at Padumagudde to Appi Kanchan's House at Katpadi in Kaup constituency | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.15 | 0.12 | 0.14 | 0.14 | 0.14 | 0.14 | 0.11 | 0.00 | Completed | PCR submitted |
24 | Impts. by concreting road from Kadike Gujjarabettyu Hoode from KM 3.40 to 5.30 | 2014-15 | RIDF-20 | UDUPI | Udupi | 1.80 | 1.44 | 1.78 | 1.78 | 1.78 | 1.78 | 1.43 | 0.00 | Completed | PCR submitted |
25 | Construction of Bridge at K M 1.4 of Malp Thottam Fisheries road | 2014-15 | RIDF-20 | UDUPI | Udupi | 0.35 | 0.28 | 0.34 | 0.34 | 0.34 | 0.34 | 0.27 | 0.00 | Completed | PCR submitted |
26 | Impts. to Road from Tarapathi Model School to Alivekodi in Paduvari village | 2014-15 | RIDF-20 | UDUPI | Kundapura | 1.00 | 0.80 | 1.00 | 1.00 | 1.00 | 1.00 | 0.80 | 0.00 | Completed | PCR submitted |
27 | Construction of Bridge at Madikal in | 2014-15 | RIDF-20 | UDUPI | Kundapura | 0.15 | 0.12 | 0.13 | 0.13 | 0.13 | 0.13 | 0.10 | 0.00 | Completed | PCR submitted |
28 | Improvements to Kodikanyana Kodi tale road Km .9 to 31 | 2014-15 | RIDF-20 | UDUPI | Kundaura | 0.37 | 0.30 | 0.37 | 0.37 | 0.37 | 0.37 | 0.30 | 0.00 | Completed | PCR submitted |
29 | Imrovements to Manoor Padukrre road at Km 6.8 to 7.4 (Chatrabttu) | 2014-15 | RIDF-20 | UDUPI | Kundapura | 0.50 | 0.40 | 0.49 | 0.49 | 0.49 | 0.49 | 0.39 | 0.00 | Completed | PCR submitted |
30 | Improvement to Sastana Kodikanyana to Kota Padukere Road at Km 2.4 to 3.6 | 2014-15 | RIDF-20 | UDUPI | Kundapura | 0.70 | 0.56 | 0.55 | 0.55 | 0.55 | 0.55 | 0.44 | 0.00 | Completed | PCR submitted |
31 | Improvements to Manoor Padukere to Kundapura Kodi road at Km 2.95 to 4.6 (Mahakali Temple) | 2014-15 | RIDF-20 | UDUPI | Kundapura | 0.40 | 0.32 | 0.38 | 0.38 | 0.38 | 0.38 | 0.30 | 0.00 | Completed | PCR submitted |
32 | Construction of road fro Hoigegudde Temple of Padupanmbur Grama Panchayat to Kadavina Bagilu | 2014-15 | RIDF-20 | DAKSHINA KANNADA | Mangalore | 2.00 | 1.60 | 2.14 | 2.14 | 2.14 | 2.14 | 1.60 | 0.00 | Completed | PCR submitted |
33 | Construction of Approach road from Kandige of Chelaiyur Grama Panchayath | 2014-15 | RIDF-20 | DAKSHINA KANNADA | Mangalore | 0.76 | 0.61 | 0.70 | 0.70 | 0.70 | 0.70 | 0.56 | 0.00 | Completed | PCR submitted |
34 | Construction of Bridge from Kandige of Chelaiyur Grama Panchayat to Mukka | 2014-15 | RIDF-20 | DAKSHINA KANNADA | Mangalore | 0.74 | 0.59 | 0.97 | 0.97 | 0.97 | 0.97 | 0.59 | 0.00 | Completed | PCR submitted |
35 | Construction of 14 Earthen Fish Ponds, Packing Shed, Water Supply and Drainage Works to Shivapura Fish Farm | 2014-15 | RIDF-20 | KOPPAL | Koppal | 1.05 | 1.00 | 0.90 | 0.90 | 0.90 | 0.90 | 0.85 | 0.00 | Completed | PCR submitted |
36 | Construction of Road connecting from Moilottu of Athikari bettu Grama Panchayath to Karnire of Balkunje Grama Panchayath via Deppuniguthu | 2015-16 | RIDF-21 | DAKSHINA KANNADA | Mangalore | 1.50 | 1.20 | 1.42 | 1.42 | 1.42 | 1.42 | 1.14 | 0.00 | Completed | PCR submitted |
37 | Improvements to road from Pangala Church to Kaipunjalu Fisheries | 2015-16 | RIDF-21 | UDUPI | Udupi | 0.60 | 0.48 | 0.41 | 0.41 | 0.41 | 0.41 | 0.33 | 0.00 | Completed | PCR submitted |
38 | Construction of bridge at Hejamadi Nadipatna approach fisheries road | 2015-16 | RIDF-21 | UDUPI | Udupi | 0.80 | 0.64 | 0.75 | 0.75 | 0.75 | 0.75 | 0.60 | 0.00 | Completed | PCR submitted |
39 | Construction of Hygiene Fish market at Sasthan | 2016-17 | RIDF-22 | UDUPI | Kundapura | 2.00 | 1.90 | 2.00 | 2.00 | 2.00 | 1.91 | 1.81 | 0.00 | Completed | PCR submitted |
40 | Construction of Hygine Fish market at Sagar | 2016-17 | RIDF-22 | SHIMOGA | Sagar | 2.40 | 2.28 | 2.40 | 2.40 | 2.40 | 1.78 | 1.69 | 0.59 | Under Progress | Work Under Progress |
41 | Construction of Hygine Fish market at N.R.PURA | 2016-17 | RIDF-22 | CHIKMAGALUR | N.R.Pura | 0.63 | 0.60 | 0.63 | 0.63 | 0.63 | 0.55 | 0.52 | 0.08 | Under Progress | Work Under Progress |
42 | Construction of Training center building at seed production center at B R Project in Bhadravathi | 2016-17 | RIDF-22 | SHIMOGA | Bhadravathi | 1.13 | 1.07 | 1.13 | 1.13 | 1.13 | 1.13 | 1.07 | 0.00 | Completed | PCR submitted |
43 | Repairs to fish pond ,construction of compound wall,fencing and yard lighting at Naraynapur | 2016-17 | RIDF-22 | BIJAPUR | Muddebihal | 0.65 | 0.62 | 0.65 | 0.65 | 0.65 | 0.65 | 0.62 | 0.00 | Completed | PCR submitted |
44 | Conversion of earthen Ponds to Masonry Ponds at Tribal Training centre at Kabini Fish Farm At H.D.Kote | 2016-17 | RIDF-22 | MYSORE | H.D.Kote | 0.50 | 0.48 | 0.50 | 0.50 | 0.50 | 0.50 | 0.48 | 0.00 | Completed | PCR submitted |
45 | Construction of Minor Fish Landing center at Belke in Bhatkal | 2016-17 | RIDF-22 | UTTAR KANNADA | Bhatkal | 2.40 | 2.28 | 0.51 | 0.51 | 0.51 | 1.21 | 1.15 | 1.13 | Under Progress | Work Under Progress |
46 | Reconstruction of Jetty Shiroor Alvegade at Kundapura | 2016-17 | RIDF-22 | UDUPI | Kundapura | 2.80 | 2.66 | 3.13 | 3.13 | 3.13 | 3.13 | 2.66 | 0.00 | Completed | PCR submitted |
47 | Construction of minor Fishing Jetty at Shashihitlu | 2016-17 | RIDF-22 | UTTAR KANNADA | Kumta | 1.00 | 0.95 | 0.86 | 0.86 | 0.86 | 0.86 | 0.81 | 0.00 | Completed | PCR submitted |
48 | Construction of Idle Berthing Jetty at Bobbarya Pade | 2016-17 | RIDF-22 | UDUPI | Udupi | 2.00 | 1.90 | 2.36 | 2.36 | 2.36 | 2.36 | 1.90 | 0.00 | Completed | PCR submitted |
49 | Construction of Asphalt Road,Bridge,Slab Culvert.Reconstruction of pond and constructiion of RCC BOX Drainage at seed production cnetre B.R.Project | 2016-17 | RIDF-22 | SHIMOGA | Bhardravati | 1.84 | 1.47 | 1.84 | 1.84 | 1.84 | 1.84 | 1.47 | 0.00 | Completed | PCR submitted |
50 | Improvement of road connecting Kalapayya Fisheries road to Chitrapura -Hosabettu - Surathkal light house sea shore road in Managalore | 2017-18 | RIDF-23 | DAKSHINA KANNADA | Mangalore | 0.87 | 0.70 | 75.79 | 75.79 | 75.79 | 0.77 | 0.55 | 0.00 | Completed | PCR submitted |
51 | Improvement to road connecting U B Rama Roa Road to Mulki-Panjinadka Main road via Kolekkadi-Uppikala of Athikari bettu GP | 2017-18 | RIDF-23 | DAKSHINA KANNADA | Mangalore | 1.53 | 1.22 | 1.53 | 1.53 | 1.53 | 1.45 | 1.16 | 0.00 | Completed | PCR submitted |
52 | Improvement of Haleyangadi Kuluvail road in Haleyangadi GP limit | 2017-18 | RIDF-23 | DAKSHINA KANNADA | Mangalore | 0.60 | 0.48 | 0.60 | 0.60 | 0.60 | 0.59 | 0.45 | 0.02 | Completed | PCR submitted |
53 | Construction of Fish Jetty for berthing of boats at Padukere side in Udyavara river of Udupi Taluk and District | 2017-18 | RIDF-23 | UDUPI | Udupi | 9.60 | 9.12 | 2.19 | 2.19 | 2.19 | 5.80 | 5.51 | 3.61 | Under Progress | Work Under Progress |
54 | Construction of Finger Jetty at Kodikanyana in Udupi Taluk and District (Extension) | 2017-18 | RIDF-23 | UDUPI | Udupi | 2.00 | 1.90 | 0.81 | 0.81 | 0.81 | 2.04 | 1.90 | 0.00 | Completed | Completed pcr pending |
55 | Extension of Fishing Jetty at Kodi Bengre in Udupi Taluk and District | 2017-18 | RIDF-23 | UDUPI | Udupi | 2.70 | 2.57 | 2.44 | 2.44 | 2.44 | 2.71 | 2.57 | 0.00 | Completed | Completed pcr pending |
56 | Improvements to road from Thrasi to Ambedkar Colony at Upper Gangolli including Kanchagodu Kodapadi road | 2017-18 | RIDF-23 | UDUPI | Kundapura | 1.60 | 1.28 | 1.60 | 1.60 | 1.60 | 1.60 | 1.28 | 0.00 | Completed | PCR submitted |
57 | Improvements to road from Hejamd to Nadipatna Sea Parallel road in Udupi Taluk and District | 2017-18 | RIDF-23 | UDUPI | Udupi | 1.00 | 0.80 | 0.82 | 0.82 | 0.82 | 0.82 | 0.65 | 0.00 | Completed | PCR submitted |
58 | Improvements to the Madikal Karkikali Fisheries Road in Kundapura Taluk and Udipi District | 2017-18 | RIDF-23 | UDUPI | Kundapura | 1.00 | 0.80 | 0.97 | 0.97 | 0.97 | 0.97 | 0.77 | 0.00 | Completed | PCR submitted |
59 | Improvements to the Fisheries Roads connecting Shiroor Alvegadde harbour in Shiroor village Kundapura Taluka | 2017-18 | RIDF-23 | UDUPI | Kundapura | 0.80 | 0.64 | 0.80 | 0.80 | 0.80 | 0.80 | 0.64 | 0.00 | Completed | PCR submitted |
60 | Extension of Malpe Jetty near Bobbarayapade in Udupi Taluk | 2018-19 | RIDF-24 | UDUPI | Udupi | 1.30 | 1.24 | 0.01 | 0.01 | 0.01 | 0.24 | 0.23 | 1.01 | Slow Moving Project | Work Under Progress |
61 | Restoration and Construction of Fish seed ponds in Gopalapura fish farm in Mandya | 2018-19 | RIDF-24 | MANDYA | Mandya | 0.91 | 0.86 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | dropped | dropped |
62 | Conversion of 15 Earthern Ponds to Masonary Ponds in Nugu Fish Farm at H D Kote | 2018-19 | RIDF-24 | MYSORE | H D Kote | 1.88 | 1.79 | 1.88 | 1.88 | 1.88 | 1.88 | 1.79 | 0.00 | Completed | PCR submitted |
63 | Conversion of 10 Earthern Ponds to Masonary Ponds in Kabini Fish Farm at H D Kote | 2018-19 | RIDF-24 | MYSORE | H D Kote | 1.90 | 1.80 | 1.90 | 1.90 | 1.90 | 1.45 | 1.38 | 0.42 | Under Progress | Work Under Progress |
64 | Construction of RCC Lining to Fish ponds, fencing, main water supply and Hatchery construction road and drainage works to Shivapura fish farm at Koppal Taluk | 2018-19 | RIDF-24 | KOPPAL | Koppal | 3.40 | 3.23 | 2.61 | 2.61 | 2.61 | 3.36 | 3.20 | 0.00 | Completed | Completed pcr pending |
65 | Restoration of Existing Fish ponds in Harangi fish farm in Somwarpet Taluk | 2018-19 | RIDF-24 | KODAGU | Somwarpet | 2.00 | 1.90 | 2.00 | 2.00 | 2.00 | 2.00 | 1.90 | 0.00 | Completed | PCR submitted |
66 | Construction of RCC Lining to Earthern ponds Nos 1 to 12 @ Menasinahally Fish Farm in Tarikere Taluk | 2018-19 | RIDF-24 | CHIKMAGALUR | Tarikere | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 1.00 | 0.95 | 0.00 | Completed | Completed pcr pending |
67 | Construction of RCC Lining to Breeding ponds , RCC Drainage works to narayan pura Fish Farm at Muddebihal Taluk , Vijayapura | 2018-19 | RIDF-24 | BIJAPUR | Muddebihal | 3.00 | 2.85 | 3.00 | 3.00 | 3.00 | 2.87 | 2.74 | 0.11 | Under Progress | Work Under Progress |
68 | Development work of Fish Farm at B R Project in Bhadravathi Taluk | 2018-19 | RIDF-24 | SHIMOGA | Bhadravathi | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 1.00 | 0.95 | 0.00 | Completed | Completed pcr pending |
69 | Construction of Hygenic Fish Market at Indi | 2018-19 | RIDF-24 | BIJAPUR | Indi | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 0.95 | 0.90 | 0.05 | Under Progress | Work Under Progress |
70 | Construction of Hygenic Fish Market at Halady | 2018-19 | RIDF-24 | UDUPI | Udupi | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 0.00 | 0.00 | 0.95 | Slow Moving Project | Work Under Progress |
71 | Construction of Hygenic Fish Market at Siruguppa | 2018-19 | RIDF-24 | BELLARY | Siruguppa | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 0.95 | 0.90 | 0.05 | Under Progress | Work Under Progress |
72 | Construction of Hygenic Fish Market at Sindhanur | 2018-19 | RIDF-24 | RAICHUR | Sindhanur | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 0.95 | 0.90 | 0.05 | Under Progress | Work Under Progress |
73 | Construction of Hygenic Fish Market at Yadagiri | 2018-19 | RIDF-24 | YADGIR | Yadgir | 1.00 | 0.95 | 1.00 | 1.00 | 1.00 | 1.00 | 0.95 | 0.00 | Completed | Completed pcr pending |
74 | Construction of Naadadoni Thangudana for Landing of Traditional fishing boats in Thota Bengre of Mangalore Taluk | 2018-19 | RIDF-24 | DAKSHINA KANNADA | Mangalore | 3.37 | 3.20 | 0.02 | 0.02 | 0.02 | 1.28 | 1.22 | 1.99 | Slow Moving Project | Work Under Progress |
75 | Construction of Auction Hall at Hangarkatte Udupi Taluk | 2018-19 | RIDF-24 | UDUPI | Kundapura | 1.01 | 0.96 | 0.36 | 0.36 | 0.36 | 0.84 | 0.80 | 0.00 | Completed | Completed pcr pending |
116.15 | 106.38 | 167.24 | 167.24 | 167.24 | 98.14 | 88.01 | 10.06 |
# | Tranche | Year | No. Of Project | Estimate Cost | NABARD Assistance | Expenditure | REC Released | Balance claim |
---|---|---|---|---|---|---|---|---|
1 | RIDF-18 | 2012-13 | 4 | 5.00 | 4.75 | 5.23 | 4.60 | 0.00 |
2 | RIDF-19 | 2013-14 | 5 | 13.50 | 12.83 | 11.63 | 10.91 | 0.00 |
3 | RIDF-20 | 2014-15 | 26 | 29.93 | 26.28 | 25.46 | 21.96 | 0.00 |
4 | RIDF-21 | 2015-16 | 3 | 2.90 | 2.32 | 2.58 | 2.07 | 0.00 |
5 | RIDF-22 | 2016-17 | 11 | 17.35 | 16.21 | 15.92 | 14.18 | 1.80 |
6 | RIDF-23 | 2017-18 | 10 | 21.70 | 19.51 | 17.55 | 15.48 | 3.63 |
7 | RIDF-24 | 2018-19 | 16 | 25.77 | 24.48 | 19.77 | 18.81 | 4.63 |
Grand total | 75 | 116.15 | 106.38 | 98.14 | 88.01 | 10.06 |
Image | Project | Tranche | Time | Action |
---|---|---|---|---|
Construction of Finger Jetty at Kodikanyana in Udupi Taluk and District (Extension) | Tranche 23 | 2021-11-17T17:20 | View | |
Construction of RCC Lining to Breeding ponds , RCC Drainage works to narayan pura Fish Farm at Muddebihal Taluk , Bijapur | Tranche 24 | 11/17/2021 16:55:51 | View | |
Construction of Idle Berthing Jetty at Bobbarya Pade | Tranche 24 | 11/17/2021 16:53:51 | View | |
Construction of minor Fishing Jetty at Shashihitlu | Tranche 22 | 11/17/2021 16:52:17 | View | |
Reconstruction of Jetty Shiroor Alvegade at Kundapura | Tranche 22 | 11/17/2021 16:48:31 | View | |
Construction of Hygenic Fish Market at Yadagiri | Tranche 24 | 9/16/2021 15:58:03 | View | |
Repairs to fish pond ,construction of compound wall,fencing and yard lighting at Naraynapur | Tranche 22 | 9/16/2021 15:57:02 | View | |
Construction of Hygenic Fish Market at Indi | Tranche 24 | 9/16/2021 15:50:53 | View | |
Improvements to the Fisheries Roads connecting Shiroor Alvegadde harbour in Shiroor village Kundapura Taluka | Tranche 23 | 9/16/2021 15:49:59 | View | |
Construction of Hygiene Fish market at Sasthan | Tranche 22 | 9/16/2021 15:48:53 | View | |
Improvements to road from Hejamd to Nadipatna Sea Parallel road in Udupi Taluk and District | Tranche 23 | 9/16/2021 15:47:32 | View | |
Improvements to road from Thrasi to Ambedkar Colony at Upper Gangolli including Kanchagodu Kodapadi road | Tranche 23 | 9/16/2021 15:46:05 | View | |
Construction of Asphalt Road,Bridge,Slab Culvert.Reconstruction of pond and constructiion of RCC BOX Drainage at seed production cnetre B.R.Project | Tranche 22 | 9/16/2021 15:44:48 | View | |
Construction of Hygenic Fish Market at Sindhanur | Tranche 24 | 9/16/2021 15:42:21 | View | |
Conversion of 10 Earthern Ponds to Masonary Ponds in Kabini Fish Farm at H D Kote | Tranche 24 | 9/16/2021 15:40:09 | View | |
Conversion of earthen Ponds to Masonry Ponds at Tribal Training centre at Kabini Fish Farm At H.D.Kote | Tranche 22 | 9/16/2021 15:38:01 | View | |
Improvement to road connecting U B Rama Roa Road to Mulki-Panjinadka Main road via Kolekkadi-Uppikala of Athikari bettu GP | Tranche 23 | 9/16/2021 15:37:08 | View | |
Improvement of road connecting Kalapayya Fisheries road to Chitrapura -Hosabettu - Surathkal light house sea shore road in Managalore | Tranche 23 | 9/16/2021 15:35:42 | View | |
Improvement of Haleyangadi Kuluvail road in Haleyangadi GP limit | Tranche 23 | 9/16/2021 15:28:51 | View | |
Construction of Hygenic Fish Market atSiruguppa | Tranche 24 | 9/16/2021 15:26:23 | View | |
Construction of RCC Lining to Earthern ponds Nos 1 to 12 @ Menasinahally Fish Farm in Tarikere Taluk | Tranche 24 | 9/16/2021 15:24:55 | View | |
Construction of Hygiene Fish market at N.R.PURA | Tranche 22 | 9/16/2021 15:20:21 | View | |
Construction of Hygiene Fish market at Sagar | Tranche 22 | 9/16/2021 15:19:16 | View | |
Extension of Fishing Jetty at Kodi Bengre in Udupi Taluk and District | Tranche 23 | 9/16/2021 15:17:53 | View | |
Construction of Training center building at seed production center at B R Project in Bhadravathi | Tranche 24 | 9/16/2021 15:14:24 | View | |
Construction of Fish Jetty for berthing of boats at Padukere side in Udyavara river of Udupi Taluk and District | Tranche 23 | 9/15/2021 16:09:02 | View | |
Improvements to the Madikal Karkikali Fisheries Road in Kundapura Taluk and Udipi Districtn 20 | Tranche 23 | 9/15/2021 15:56:00 | View | |
Construction of Auction Hall at Hangarkatte Udupi Taluk | Tranche 24 | 9/15/2021 15:48:36 | View | |
Development work of Fish Farm at B R Project in Bhadravathi Taluk | Tranche 24 | 9/15/2021 13:05:59 | View | |
Construction of RCC Lining to Fish ponds, fencing, main water supply and Hatchery construction road and drainage works to Shivapura fish farm at Koppal Taluk | Tranche 24 | 9/15/2021 12:51:33 | View | |
Conversion of 15 Earthern Ponds to Masonary Ponds in Nugu Fish Farm at H D Kote | Tranche 24 | 9/15/2021 12:45:52 | View | |
Conversion of earthen Ponds to Masonry Ponds at Tribal Training centre at Kabini Fish Farm At H.D.Kote | Tranche 24 | 9/15/2021 12:40:04 | View | |
Restoration of Existing Fish ponds in Harangi fish farm in Somwarpet Taluk | Tranche 24 | 9/15/2021 12:38:55 | View |